Question: The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost

The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $ 9. There is a carrying cost of $ 0.02 per unit per week. Beginning inventory is 70 units.

The MRP gross requirements for Item X are shown here

Use the least total cost or the least unit cost lot- sizing method to determine when and for what quantity the first order should bereleased.

WEEK 1 234 5 6 78 9 10 Gross requirements 20 10 15 45 10 30 100 20 40 150

Step by Step Solution

3.44 Rating (167 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Period 1 2 3 4 5 6 7 8 9 10 Gross Requirements 20 10 15 45 10 30 100 20 40 150 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

287-B-M-L-S-C-M (1708).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!