Question: The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $ 9. There is a carrying cost of $ 0.02 per unit per week. Beginning inventory is 70 units.
.png)
.png)
Use the least total cost or the least unit cost lot- sizing method to determine when and for what quantity the first order should bereleased.
WEEK 1 234 5 6 78 9 10 Gross requirements 20 10 15 45 10 30 100 20 40 150
Step by Step Solution
★★★★★
3.44 Rating (167 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Period 1 2 3 4 5 6 7 8 9 10 Gross Requirements 20 10 15 45 10 30 100 20 40 150 ... View full answer