Question: The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost
The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $ 10. There is a carrying cost of $ 0.01 per unit per week. Beginning inventory is 90 units.
.png)
Use the least total cost or the least unit cost lot sizing method to determine when and for what quantity the first order should bereleased.
WEEK 3 4567 8 9 10 Gross requirements 30 50 10 20 70 0 20 60 200 50
Step by Step Solution
3.30 Rating (159 Votes )
There are 3 Steps involved in it
Least Total Cost Period 1 2 3 4 5 6 7 8 9 10 Gross Requirements 30 50 10 20 70 80 20 60 200 50 Proj... View full answer