Question: The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost

The MRP gross requirements for Item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $ 10. There is a carrying cost of $ 0.01 per unit per week. Beginning inventory is 90 units.

The MRP gross requirements for Item A are shown here

Use the least total cost or the least unit cost lot sizing method to determine when and for what quantity the first order should bereleased.

WEEK 3 4567 8 9 10 Gross requirements 30 50 10 20 70 0 20 60 200 50

Step by Step Solution

3.30 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Least Total Cost Period 1 2 3 4 5 6 7 8 9 10 Gross Requirements 30 50 10 20 70 80 20 60 200 50 Proj... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

287-B-M-L-S-C-M (1707).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!