Question: Given the information below, what is the time required to produce the 500th unit? (Use the formula: Tn=T1nb) The learning curve is 90% The labor
Given the information below, what is the time required to produce the 500th unit?
(Use the formula: Tn=T1nb)
| The learning curve is 90% |
| The labor rate is $15 an hour |
| It takes 485 hours of labor to produce the first unit |
a) 188.58
b) 195.31
c) 259.86
d) 301.10
e) 0
What is the percent of labor cost savings?
a) 37.92%
b) 46.42%
c) 59.73%
d) 38.88%
e) 61.12%