Question: Given the information below you are asked to apply project management techniques to the proposed project to address both the Planning Phase and the Implementation
Given the information below you are asked to apply project management techniques to the proposed project to address both the Planning Phase and the Implementation Phase of the project. See also Table of data below giving and overview of the project, a Work Breakdown Structure WBS durations and costrelated information. This will be handed out in class.
Construct a suitable network diagram which shows the precedence logic of each activity. You should use activityonarrow or precedence method. This may be done manually on paper but a higher grade may be obtained with the help of software todraw the diagram. Use the diagram to calculate each activity Early start Date number and hence determine the earliest likely overall completion time. Taking this day number as a target for completion, calculate the Latest Times for each activity or node. Finally
calculate the floats and show the critical path.
From your network information using an Excel spreadsheet to one day accuracy produce a Gantt chart based on Early started times. Explain the limitations of the Gantt chart on its own and how an activity network assisted by computer software could be used to monitor the actual progress in terms of timing throughout the project and what steps might be taken to improve the timing schedule if the project were required to becompleted in two months.
Using the given cost estimate information calculate total cost by Group and Overall, without and then with Contingency. Construct a budget BCWS spreadsheet with activities down the left hand side and a month by month calendar as the XAxis. Apply a suitable method of allocating the cost of each activity evenly over each month of its duration. Allocate costs to months. The sheet should show subtotal costs for each activity group and overall per month. Construct a graph against time for the periodic
spend and the same information on a cumulative basis.
IMPORTANT NOTES:
You should clearly identify the separate sections of your report before submitting it
Section Q Q should be in sequence.
A table of activities and cost information is attached below. This is essential for some of the above tasks and can also be used as a worksheet.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
