Question: Given the information in the table below, what is the critical path for this project? Activity Immediate Predecessors Duration # of Weeks Activity can be

Given the information in the table below, what is

Given the information in the table below, what is the critical path for this project? Activity Immediate Predecessors Duration # of Weeks Activity can be Crashed 1 Direct Cost Per Week . 5 $800 B 4 1 $300 AB 3 D 1 NN E 1 $375 $400 $2000 $1000 F E 2 5 5 5 2 G D, F 1 A-C-D-G A-C-E-F-G B-C-E-F-G B-C-D-G