Question: Given the information in the table below, what is the critical path for this project? Activity Immediate Predecessors Duration # of Weeks Activity can be

Given the information in the table below, what is the critical path for this project?

Activity

Immediate Predecessors

Duration

# of Weeks Activity can be Crashed

Direct Cost Per Week

A

-

5

1

$800

B

-

4

1

$300

C

A, B

3

-

-

D

C

2

1

$375

E

C

2

1

$400

F

E

5

2

$2000

G

D, F

5

1

$1000

Group of answer choices

A-C-D-G

A-C-E-F-G

B-C-E-F-G

B-C-D-G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!