Question: Given the information in the table below, what is the critical path for this project? Activity Immediate Predecessors Duration # of Weeks Activity can be
Given the information in the table below, what is the critical path for this project?
| Activity | Immediate Predecessors | Duration | # of Weeks Activity can be Crashed | Direct Cost Per Week |
| A | - | 5 | 1 | $800 |
| B | - | 4 | 1 | $300 |
| C | A, B | 3 | - | - |
| D | C | 2 | 1 | $375 |
| E | C | 2 | 1 | $400 |
| F | E | 5 | 2 | $2000 |
| G | D, F | 5 | 1 | $1000 |
Group of answer choices
A-C-D-G
A-C-E-F-G
B-C-E-F-G
B-C-D-G