Question: What is the critical path for this project? Activity Immediate Predecessors Duration # of Weeks Activity can be Crashed Direct Cost Per Week A 5

What is the critical path for this project?
What is the critical path for this project? Activity Immediate Predecessors Duration # of Weeks Activity can be Crashed Direct Cost Per Week A 5 1 $800 B 4. 1 $300 C AB 3 D NI 2 1 $375 | | E 2 1 $400 F E 2 $2000 5 5 G DF 1 $1000 O A-C-D-G B-C-E-F-G O A-C-E-F-G O B-C-D-G