Question: Given the information provided below, the latest start time for activity C is: A precedence network with 7 nodes.In the precedence network the start node

Given the information provided below, the latest start time for activity C is:
A precedence network with 7 nodes.In the precedence network the start node is A and the end node is G. The paths in the network are as follow:A-B-E-GA-D-G; A-B-D-G; A-C-F-G; A-C-D-G;The time associated with each node is as follows: A,4; B,8; C,9; D.9; E,7; F.2; and G.5.
Multiple Choice
5
19
4
13
12