Question: Given the network in Figure below ( the listed numbers are the activity times; example: A activity time is 5 ; C activity time is

Given the network in Figure below ( the listed numbers are the activity times; example: A activity time is 5; C activity time is 6, etc.), the critical path is
A, C, F,H
B,D,E,F,H
A, C,E,G,H
B,D,E,G,H
B,D,G,H