Question: Given the project information below, for how many days the project can be possibly shortened? (ignore the cost of crashing the project duration) ES DEF

Given the project information below, for how manyGiven the project information below, for how many

Given the project information below, for how many days the project can be possibly shortened? (ignore the cost of crashing the project duration) ES DEF Act FF LS TF LF 0 60 60 A 60 80 140 60 140 0 60 000 Start 0 0 14060 200 E 140 200 40 100 140 0 40 40 B D 40 40 40 140 Activity Days it can be shortened A 5 B 8 11 D 54 E The maximum number of days the project can be shortened is