Question: Given the project network and baseline information below. Create a phase time-phased budget for the project. (4 marks) Cost Per Week (Rands) 200 200 200
Given the project network and baseline information below. Create a phase time-phased budget for the project. (4 marks) Cost Per Week (Rands) 200 200 200 600 200 600 200 600 200 400 500 100 300 400 400 400 400 300 400 200 200 100 300 4. Develop a status report for the project at the end of period 8 given that at the end of this period, activities A, B, C, D, E are 100; 100; 100; 25%; and 33% complete respectively. Activity F has not started at this stage. The actual costs for incurred for these activities are R300; R2200; R1500; R300; 300. What information are you prepared to tell the customer about the status of the project at the end of period 8? (6 marks)