Question: Given the project network and baseline information below Figure 1 and Table 2: Calculate the CPI and SPI for activity A after period 2 and

Given the project network and baseline information below Figure 1 and Table 2: Calculate the CPI and SPI for activity A after period 2 and mark the correct answer from the given choices? ID Budget ($000) 1 2 3 4 5 6 7 8 9 10 11 12 A 40 10 10 10 10 B 32 8 4 8 4 8 C 48 12 12 12 12 D 18 6 2 2 2 6 E 28 8 8 12 F 40 20 20 Total 206 18 16 16 14 20 26 22 26 2 6 20 20 Cumulative 18 32 50 64 84 110 132 158 160 166 186 206 Status Report Ending Period-2 Task % Complete EV AC PV CV SV Schedule On / Behind / Ahead BudgetOn / Over / Under A 60% 23 B 50% 10 Cumulative Totals 34