Question: Given the project network below. Activity times are in weeks. What is the earliest time that Activity 1 will be completed? What is the latest


Given the project network below. Activity times are in weeks. What is the earliest time that Activity 1 will be completed? What is the latest that Activity 3 could be started? Week 17 Week 24 Week 10 Week 31 Question 6 What is the slack associated with Activity 5? 6 weeks 21 weeks 3 weeks 15 weeks What is the critical path? 1478 2. 5=78 2. 68 1-3-8