Question: Question 1 (0.5 points) Given the project network and activity times in weeks) below. What is the completion time of the project? 13 10 9

Question 1 (0.5 points) Given the project network
Question 1 (0.5 points) Given the project network
Question 1 (0.5 points) Given the project network and activity times in weeks) below. What is the completion time of the project? 13 10 9 22 023 O 24 18 Given the project network and activity times (in weeks) below. The (ES, EF] for activity (4-5) are: 13 10 O ES-17, EF-22 ES=19, EF-24 ES-13, EF-18 ES=18, EF-23