Question: Given the project network below. Activity times are in weeks. Start O Week 15 Week 10 O Week 7 10 O Week 0 25 15



Given the project network below. Activity times are in weeks. What is the earliest time that Activity 1 will be completed? Week 15 Week 10 Week 7 Week 0 What is the earliest time that Activity 4 will be started? Week 15 Week 24 Week 10 Week 14 Question 3 What is the earliest time that Activity 4 will be finished? Week 0 Week 24 Week 10 Week 17 What is the earliest time that Activity 7 will be finished? Week 31 Week 28 Week 7 Week 24 Question 5 What is the latest that Activity 3 could be started? Week 31 Week 24 Week 17 Week 10 What is the slack associated with Activity 5? 6 weeks 3 weeks 15 weeks 21 weeks What is the critical path? 1478 268 138 2578