Question: Given the project network shown below, the earliest finish time for activity e is: Multiple Choice a 16 b 11 c 24 d 13 e
Given the project network shown below, the earliest finish time for activity e is:
Multiple Choice
a 16
b 11
c 24
d 13
e 22