Question: Given the project within the table below, calculate the following: a. What is the project length? b. What activities are on the critical path? c.

Given the project within the table below, calculate the following: a. What is the project length? b. What activities are on the critical path? c. How much slack is in activity A ? , and activity B ? d. What is the Late Start / Late Finish for activity B? e. What would happen to the overall project length if activity E was delayed by 4 days, now taking a total of 14 days