Question: Given the project within the table below, calculate the following: a. What is the project length? b. What activities are on the critical path? c.

 Given the project within the table below, calculate the following: a.

Given the project within the table below, calculate the following: a. What is the project length? b. What activities are on the critical path? c. How much slack is in activity B ? d. What is the Late Start / Late Finish for activity A? f. What if activity A was delayed by 4 hours (now taking 8 hours), what impact would it have on the overall project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!