Question: Given the project within the table below, calculate the following: a. What is the critical path b. How much slack does activity A have? c.

Given the project within the table below, calculate the following: a. What is the critical path b. How much slack does activity A have? c. How much slack does activity B have? d. How much slack does activity G have? e. For activity E, what is the late start the late finish and it's length
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
