Question: Given the project within the table below, calculate the following: a. What is the critical path and it's length b. How much slack does activity



Given the project within the table below, calculate the following: a. What is the critical path and it's length b. How much slack does activity A have? c. How much slack does activity B have? d. How much slack does activity G have? e. For activity E, what is the late start , and the late finish e. For activity E, what is the late star , and the late finish e. For activity E, what is the late start , and the late finish [Select]15171218