Question: Given the project within the table below, calculate the following: Activity, Duration (hours), Immediate Predecessors A 4 none B 9 A C 8 none D
Given the project within the table below, calculate the following:
Activity, Duration (hours), Immediate Predecessors
A 4 none
B 9 A
C 8 none
D 7 C
E 2 B, D
F 3 A, E
G 7 C, F
H 6 G
a. What is the project length?
b. What activities are on the critical path?
c. How much slack is in activity B?
d. What is the Late Start / Late Finish for activity A?
f. What if activity A was delayed by 4 hours (now taking 8 hours), what impact would it have on the overall project?