Question: Given the project within the table below, calculate the following: Activity, Duration (hours), Immediate Predecessors A 4 none B 9 A C 8 none D

Given the project within the table below, calculate the following:

Activity, Duration (hours), Immediate Predecessors

A 4 none

B 9 A

C 8 none

D 7 C

E 2 B, D

F 3 A, E

G 7 C, F

H 6 G

a. What is the project length?

b. What activities are on the critical path?

c. How much slack is in activity B?

d. What is the Late Start / Late Finish for activity A?

f. What if activity A was delayed by 4 hours (now taking 8 hours), what impact would it have on the overall project?