Question: Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors TA 4 B 3 -- C 8 A, B D

Given the project within the table below,
Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors TA 4 B 3 -- C 8 A, B D 7 E B, C 2. 3 F D, E G 7 F > a. What is the project length? (Select] b. What activities are on the critical path? [Select ] c. How much slack in in activity B? (Select] d. What is the Late Start / Late Finish for activity D