Question: Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors A 4 B 3 8 A, B D 7 MW

Given the project within the table below,

Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors A 4 B 3 8 A, B D 7 MW E 2 B, C 3 D, E G 7 F a. What is the project length? [Select] b. What activities are on the critical path? [Select] c. How much slack in in activity B? [Select] d. What is the Late Start / Late Finish for activity D? [Select] f. What if activity D was delayed by 8 hours (now taking 15 hours), what impact would it have on the overall project? [Select]