Question: Given the project within the table below, calculate the following: table [ [ Activity , table [ [ Duration ] , [ (

Given the project within the table below, calculate the following:
\table[[Activity,\table[[Duration],[(hours)]],\table[[Immediate],[Predecessors]]],[A,4,None],[B,8,None],[C,6,A],[D,7,B, C],[E,3,D],[F,1,E],[G,5,E, F],[H,4,G]]
a. What is the project's minimum completion time?
 Given the project within the table below, calculate the following: \table[[Activity,\table[[Duration],[(hours)]],\table[[Immediate],[Predecessors]]],[A,4,None],[B,8,None],[C,6,A],[D,7,B,