Question: Given the project within the table below, calculate the following: Activity Duration ( hours ) Immediate Predecessors A 4 - B 3 - C 1
Given the project within the table below, calculate the following:
Activity Duration hours Immediate Predecessors
A
B
C
D BC
E D
F E
G AF
a What is the critical path
Select
and it's length
Select
b How much slack does activity A have?
Select
c How much slack does activity B have?
Select
d How much slack does activity G have?
Select
e For activity E what is the late start
Select
and the late finish
Select