Question: Given the project within the table below, calculate the following: Activity Duration ( hours ) Immediate Predecessors A 4 - B 3 - C 1

Given the project within the table below, calculate the following:
Activity Duration (hours) Immediate Predecessors
A 4-
B 3-
C 10-
D 7 B,C
E 1 D
F 1 E
G 5 A,F
a. What is the critical path
[ Select ]
and it's length
[ Select ]
b. How much slack does activity A have?
[ Select ]
c. How much slack does activity B have?
[ Select ]
d. How much slack does activity G have?
[ Select ]
e. For activity E, what is the late start
[ Select ]
, and the late finish
[ Select ]
.