Question: Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors A 4 B 3 C 10 D 7 |B.C F

Given the project within the table below,

Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors A 4 B 3 C 10 D 7 |B.C F 1 D F 1 E G 5 |A,F a. What is the critical path C,D,E,F,G and it's length 24 hours b. How much slack does activity A have? [Select] c. How much slack does activity B have? [Select] d. How much slack does activity G have? [Select] e. For activity E, what is the late start (Select] and the late finish [Select]