Question: Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors A 4 None B 5 None 10 D 7 B,C

Given the project within the table below,
Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors A 4 None B 5 None 10 D 7 B,C E 3 D F 1 E G 5 EF a. What is the project's minimum completion time? [Select] b. What is the critical path in the project? Select] c. What is the slack in activity B? (Select) d. What is the Early Start and Early Finish for Activity D? [Select] e. What is the Late Start and Late Finish for activity B? (Select)