Question: Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors A 4 -- B 3 -- C 8 A D
Given the project within the table below, calculate the following:
| Activity | Duration (hours) | Immediate Predecessors |
| A | 4 | -- |
| B | 3 | -- |
| C | 8 | A |
| D | 7 | B, C |
| E | 2 | D |
| F | 3 | E |
| G | 7 | E, F |
What is the project length?
What activities are on the critical path?
What is the late start/late finish for activity F?