Question: Given the project within the table below, calculate the following: Activity Duration (hours) Immediate Predecessors A 4 -- B 3 -- C 8 A D

Given the project within the table below, calculate the following:

Activity Duration (hours) Immediate Predecessors
A 4 --
B 3 --
C 8 A
D 7 B, C
E 2 D
F 3 E
G 7 E, F

What is the project length?

What activities are on the critical path?

What is the late start/late finish for activity F?