Question: Given the project within the table below, calculate the following: Duration Immediate Activity (hours) A 4 B Predecessors none A AB C 2 none F

Given the project within the table below,
Given the project within the table below, calculate the following: Duration Immediate Activity (hours) A 4 B Predecessors none A AB C 2 none F 3 D. E G 7 F a. What is the project length? [Select] b. What activities are on the critical path? [Select] c. How much slack is in activity B? [Select] d. What is the Late Start / Late Finish for activity E? [Select] f. What if activity E was delayed by 8 hours (now taking 10 hours), what impact would it have on the overall project? [Select] C D E 19 8 7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!