Question: Given the project within the table below, calculate the following: Activity A B C D E F G Duration (hours) 4 5 10 7
Given the project within the table below, calculate the following: Activity A B C D E F G Duration (hours) 4 5 10 7 3 1 01 Immediate Predecessors None None A B, C D E LL E, F a. What is the project's minimum completion time? [Select] b. What is the critical path in the project? [Select] c. What is the slack in activity B? [Select] Given the project within the table below, calculate the following: Activity A B C D E F G Duration (hours) 4 5 10 7 3 1 01 Immediate Predecessors None None A B, C D E LL E, F a. What is the project's minimum completion time? [Select] b. What is the critical path in the project? [Select] c. What is the slack in activity B? [Select]
Step by Step Solution
3.38 Rating (157 Votes )
There are 3 Steps involved in it
ANSWER To calculate the projects minimum completion time critical path and slack for activity B lets analyze the given information Activity Duration hours Immediate Predecessors A 4 None B 5 None C 10 ... View full answer
Get step-by-step solutions from verified subject matter experts