Question: Given the table below: Activity A B C D E F G H I Dependency A A A B B,C C,D FG E,F,H Duration
Given the table below: Activity A B C D E F G H I Dependency A A A B B,C C,D FG E,F,H Duration (weeks) 2 10 8 4 6 12 4 6 3 # Resources 3 4 8 6 4 2 10 9 2 a) Develop the project network b) Build the Gantt chart c) Assuming there are only 15 resources available for the duration of this project, how can the schedule be adjusted to level the resources? Revise the Gannt chart to reflect this resource availability.
Step by Step Solution
3.40 Rating (144 Votes )
There are 3 Steps involved in it
Answer a To develop the project network we need to identify the activities and their dependencies Th... View full answer