Question: Given the table below, assuming that there are only 8 resources available at any time: begin { tabular } { | c | c

Given the table below, assuming that there are only 8 resources available at any time:
\begin{tabular}{|c|c|c|c|}
\hline Activity & \begin{tabular}{c}
Duration \\
(weeks)
\end{tabular} & Dependency & Resources \\
\hline A & 12 & & 4\\
\hline B & 7 & & 2\\
\hline C & 4 & & 3\\
\hline D & 7 & A & 5\\
\hline E & 1 & B & 3\\
\hline F & 3 & B,C & 4\\
\hline G & 6 & D,E & 4\\
\hline I & 2 & D,E & 5\\
\hline J & 4 & F & 3\\
\hline K & 6 & G & 3\\
\hline
\end{tabular}
a) Provide the full network diagram (6 marks)
b) Provide the original Gantt chart with all resources (6 marks)
c) Provide the detailed steps (how and why) for the updated the schedule based on resource constraints (\(121/3\) marks)
d) Provide the final Gantt chart (6 marks)
e) What is the final project duration? (3 marks)
 Given the table below, assuming that there are only 8 resources

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!