Question: Given the table below, assuming that there are only 8 resources available at any time: begin { tabular } { | c | c
Given the table below, assuming that there are only resources available at any time:
begintabularcccc
hline Activity & begintabularc
Duration
weeks
endtabular & Dependency & Resources
hline A & & &
hline B & & &
hline C & & &
hline D & & A &
hline E & & B &
hline F & & BC &
hline G & & DE &
hline I & & DE &
hline J & & F &
hline K & & G &
hline
endtabular
a Provide the full network diagram marks
b Provide the original Gantt chart with all resources marks
c Provide the detailed steps how and why for the updated the schedule based on resource constraints marks
d Provide the final Gantt chart marks
e What is the final project duration? marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock