Question: Given the table of activities below which represents the project activities of a software development project answer the following questions: - draw the networking diagram?

  1. Given the table of activities below which represents the project activities of a software development project answer the following questions: -
  1. draw the networking diagram?
  2. List the Paths and identified the Critical Path?
  3. Compute ES, EF, LS, LF (05 and identified the slack for each activity?

Name of Activity

Predecessor Activity

Duration (Weeks)

A

-

8

B

A

13

C

A

9

D

A

12

E

B

14

F

B

8

G

D

7

H

C,E,G

12

I

C,E,G

9

J

E,H

10

K

I,J

7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!