Question: Given the time-phased work packages and network, complete the baseline budget for the project. 9 9 9 WP Design WP Survey WP Report 7 8

Given the time-phased work packages and network,

Given the time-phased work packages and network,

Given the time-phased work packages and network, complete the baseline budget for the project. 9 9 9 WP Design WP Survey WP Report 7 8 8 00 7 7 8 7 8 8 8 Project Network 0 1 3 3 2 3 0 Design Survey Report 0 3 3 3 6 3 Time-phased budget ($ 000) Week Week 4 Week 5 Week 6 Week 7 Task Budget Week 1 Week 2 Week 3 Week 8 Week 9 Week 10 Week 11 Week 12 27 9 9 9 45 Design Survey Report Total 23 95 Cumulative