Question: Week 7 Week 8 Week 9 Week 10 Given the time-phased work packages, complete the baseline budget for the project. Time-phased budget ($ 000)

Week 7 Week 8 Week 9 Week 10 Given the time-phased work

Week 7 Week 8 Week 9 Week 10 Given the time-phased work packages, complete the baseline budget for the project. Time-phased budget ($ 000) Week Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 7 Task Activity 1 Budget 7 Activity 2 25 Activity 3 31 Activity 4 24 Activity 5 18 Total 105 Cumulative 9 6 8 7 8 6 8 8 8 9