Question: Given this AON network and the data on the following slide, determine the expected project completion time and variance, and the probability that the project

Given this AON network and the data on the following slide, determine the expected project completion time and variance, and the probability that the project will be completed in 28 days or less.

Given this AON network and the data on the
3. Given this AON network and the data on the following slide, determine the expected project completion time and variance, and the probability that the project will be completed in 28 days or less. Time Estimates (weeks) Activity a m b 2 3 7 3 1 10 5 3 13 7 5