Question: Given this information about activity H: ES = 27, EF = 34, LS = 42, and LF = 49, we can determine that the amount

Given this information about activity H: ES = 27, EF = 34, LS = 42, and LF = 49, we can determine that the amount of slack associated with the activity is: a. 15 b. 7 c. 22 d. 8 e. 12