Question: Given this information about activity H: ES = 27, EF = 34, LS = 42, and LF = 49, we can determine that the duration

Given this information about activity H: ES = 27, EF = 34, LS = 42, and LF = 49, we can determine that the duration of activity H is: a. 7 b. 22 c. 15 d. 8 e. 12