Question: Given three jobs, A , B , C which take 2 0 0 , 1 0 0 , and 3 0 0 units of time

Given three jobs, A, B, C which take 200,100, and 300 units of time to complete. They arrive at the scheduler at very close to the same time, so that the scheduler can choose the ordering of the jobs simultaneously.
with the FIFO scheduler, the jobs are run in alphabetical order, what is the average turnaround time? what is the average response time?
ATAT =200+100+300/3=200 units and ART time should be 0 for the first job.
with the SJF scheduler, what is the average turnaround time? What is the average response time?
ATAT =100+200+300/3=200 units and ART should be 0 for the first job.