Question: Glenn has recently been appointed project manager and is using three-point estimating to calculate the estimates for activity duration. For Activity D, he has the
Glenn has recently been appointed project manager and is using three-point estimating to calculate the estimates for activity duration. For Activity D, he has the following information: P = 9, O = 4, M = 5. What is the result of this estimate? Select one: 18 weeks 6 weeks 33.33 weeks 3 Weeks