Question: Golf Carts Inc. must set up an assembly line for golf carts. Forecasts show that 8 units per day should be produced. The plant operates
Golf Carts Inc. must set up an assembly line for golf carts. Forecasts show that 8 units per day should be produced. The plant operates one eight-hour shift each day and runs the line continuously during the shifts. The tasks required, task times, and precedence relationships are as follows:
| Task | Time (Minutes) | Predecessors |
| A | 13 | |
| B | 12 | |
| C | 23 | |
| D | 30 | A, B |
| E | 16 | C |
| F | 28 | D |
| G | 11 | E, F |
b. What is the takt time? (Round your answer to the nearest whole number.)
c. What is the theoretical number of workstations? (Round up your answer to the next whole number.)
d. Assign the tasks to the workstations to balance the line using the longest operating time rule.
e. What is the efficiency of the balanced line? (Round your answer to 1 decimal place.)
f. If demand increased to 9 units per day, what would be the new takt time? (Round your answer to the nearest whole number.)