Question: Golf Carts Inc. must set up an assembly line for golf carts. Forecasts show that 10 units per day should be produced. The plant operates

Golf Carts Inc. must set up an assembly line for golf carts. Forecasts show that 10 units per day should be produced. The plant operates one eight-hour shift each day and runs the line continuously during the shifts. The tasks required, task times, and precedence relationships are as follows:

Golf Carts Inc. must set up an assembly line for

a. Draw the precedence diagram.
b. What is the takt time?
c. What is the theoretical number of workstations?
d. Assign the tasks to the workstations to balance the line using the longest operating time rule.
e. What is the efficiency of the balanced line?
f. If demand increased to 12 units per day, what changes would be needed, if any?

Task Time (minutes) Predecessors 12 10 16 24 14 30 15 A, B E. F

Step by Step Solution

3.53 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a b Takt time 8 hoursday x 60 minhour 10 unitsday 48 minutes per u... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

434-B-M-L-S-C-M (2292).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!