Question: Gordon has been assigned to a task that takes 5d of duration. His boss thinks he can finish the task in 4 days, because he

Gordon has been assigned to a task that takes 5d of duration. His boss thinks he can finish the task in 4 days, because he doesn't realize Gordon is also working on other tasks in that time period. He changes the duration to 4d and clicks OK. Gordon tells his boss that he is only available 50% of the available time. The boss changes the Units to 50% and clicks OK. What is the new duration?

Question 16 options:

2 days 4 days 6 days 8 days