Question: gs Activity Immediate Predecessor Optimistic Most Probable Pessimistic 3 4 4 5 5 B 3 5 7. C A 4 5 6 D A 2

gs Activity Immediate Predecessor Optimistic Most
gs Activity Immediate Predecessor Optimistic Most
gs Activity Immediate Predecessor Optimistic Most Probable Pessimistic 3 4 4 5 5 B 3 5 7. C A 4 5 6 D A 2 3 15 E B 6 10 14 F B 8. 9 13 G c 10 15 1 20 H D 5 00 E ON 8 10 FGH 8 10 12 3. What is the expected overall project time? (weeks)