Question: Answer #2 Activity Immediate Predecessor Optimistic Most Probable Pessimistic 3 5 5 B A 5 7 A 4 5 6 D A 2 3 5

Answer #2 Answer #2 Activity Immediate Predecessor
Activity Immediate Predecessor Optimistic Most Probable Pessimistic 3 5 5 B A 5 7 A 4 5 6 D A 2 3 5 E B 6 10 14 T7 B 8 9 13 G c 10 15 20 H D 5 8 11 E 6 8 10 U F.G.H 8 10 12 1. What is the Earliest Start time for activity ? 2. What is the Latest Start time for activity B