Question: Activity Immediate Predecessor Optimistic Most Probable Pessimistic 3 4 5 B A 3 5 7 C A 4 5 6 D A 2 3 5

Activity Immediate Predecessor Optimistic Most
Activity Immediate Predecessor Optimistic Most
Activity Immediate Predecessor Optimistic Most Probable Pessimistic 3 4 5 B A 3 5 7 C A 4 5 6 D A 2 3 5 E B 6 10 14 F B 00 9 13 G C 10 15 20 H D 15 8 11 E 6 co 10 FGH 8 10 12 1. What is the earliest Start time for activity J? 2. What is the Latest Start time for activity B? 3. What is the expected overall project time? (weeks) 4. What is the critical path? 5. What is the total variance for the critical path? 6. What is the total standard deviation? 7. Which activity has the most slack? 8. What is the probability that this project will take more than 35 weeks? (Used decimal places

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!