Question: H WN C D E F Most Worst Optimistic Likely Case Expected Duration Duration Duration Duration 1 Task Successors (days) (days) (days) (days) Variance D

H WN C D E F Most Worst Optimistic Likely Case
H WN C D E F Most Worst Optimistic Likely Case Expected Duration Duration Duration Duration 1 Task Successors (days) (days) (days) (days) Variance D 1 2 3 B EF 1 2 3 4 C G 2 3 4 5 D H 3 7 6 E H 4 5 8 7 F J 3 5 7 8 G 1 3 5 7 9 H J 4 8 10 J 1 2 3 11 none 2 4 6 12 13 14 What is/are the critical paths? 15 What is the project duration and variance? Duration: Variance 16 What is the likelihood of finishing the project in 16 days? Z score 17 Probability 18 Interpret NORMDIST calculation here: 19 20 21 22 I--- unste DERIData