Question: Halfway through its work, the team found that they did not estimate enough time to complete the techrical and infrastructure requirements. The project manager has

Halfway through its work, the team found that they did not estimate enough time to complete the techrical and infrastructure requirements. The project manager has requested a change to have this new work added to the scope and additional time added to the schedule. What should the project manager do next?
A Create new metric baselines.
B
Review the impact of the change and bring it to the change control board.
Update the scope and schedule baselines.
D Update the risk register.