Question: Halfway through their work, a team found that they did not estimate enough time to complete the technical and infrastructure requirements. The project manager has
Halfway through their work, a team found that they did not estimate enough time to complete the technical and infrastructure requirements. The project manager has requested a change to have this new work be added to the scope and additional time added to the schedule. The change control board approved the change. What should the project manager do next?This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A Update the project charter. option B Update the risk register. option C Update the scope and schedule baselines. option D Perform the work