Halo Enterprises recently experienced a fire, forcing the company to use incomplete information to analyze operations. Consider
Question:
Halo Enterprises recently experienced a fire, forcing the company to use incomplete information to analyze operations. Consider the following data and assume that all materials purchased during the period were used in production: Direct materials: Standard price per pound: $9 Actual price per pound: $8 Price variance: $20,000F Total of direct-material variances: $2,000F Direct labor: Actual hours worked: 40,000 Actual rate per hour: $15 Efficiency variance: $28,000F Total of direct-labor variances: $12,000U Halo completed 12,000 units. Required: Determine the following: (1) actual materials used, (2) direct-material quantity variance, (3) direct-labor rate variance, (4) standard labor rate per hour, and (5) standard labor time per finished unit.